High End Music Venue
An enquiry was made from a music venue in the north of the country.
The problem was they had been served with a noise abatement order and would not be allowed to operate. They had 2 large events booked in 6 weeks time. These events were profitable and they could not afford to loose the business.
Our surveyor was sent there as a matter of urgency.
The surveyor found the following problems
- The noise generated at the speakers was 128db.
-
The existing structure, particularly the roof was weak in terms of noise suppression. It was,
- Glass panels in roof.
- Very thin roof with 100mm void between internal covering and external skin.
- The doors were single and directly to the outside
- Adjacent rooms had windows and other weaknesses.
Design limitations
- The roof angle iron trusses could not be loaded with any more weight.
- The width and length of the room meant that new structural beams would be required.
Design
An initial design was made and priced within 3 days. Including structural engineer calculations.
This was outside the affordable budget of the customer, so the design was altered and re-priced. This was agreed and a confirmatory site meeting took place 7 days later.
Project liaison
We made contact with the local environmental health enforcement officers and explained what was going to be done.
They were invited to the venue both before and during the construction to see what it involved.
Time
From the time we were able to start on site we had 3½ weeks to get ready for the 2 major events. The timings were very tight, some smaller details were not complete, but the major structure was in place and working.
Developers
In addition to the text some pictures are needed!
Also;
Often problems can arise even if robust detail has been followed, also a property may have failed the noise test.
We will;
- Carry out a survey of the construction
- Review the test results/report
- Identify problem areas.
- Produce a report with recommendations
- If required carry out further detailed examinations
- Install additional noise suppression measures.
Contract & installation
- Blow acoustic pugging into existing void ( Area 330m²)
- Install 3 n˚ new steel portal frames
- Acoustically box out all roof lights.
- Construct new timber joists onto portal frames in 150 x 50 timber at 600mm centres
- On to p of timber fit are layer of Soundcheck board and are layer of super mass loaded vinyl.
- To underside of joists fix additional layer of super mass loaded vinyl.
- To underside of joists fix additional layer of super mass loaded vinyl.
- Fix resilient bars at 600mm centres.
- Fix 2 layers of Soundcheck board
- Acoustically box windows.
- Construct acoustic wall at one end of hall
- Construct new partitions with new sets of double fire doors
Summery
- Survey
- Design in conjunction with structural engineer
- Cost calculated and adjusted with customer
- Liaison with local authority
- Installation
- Liaison with sound people & local council as construction progressed
- Post installation liaison with local council
For more information, please contact us on 0845 845 2025.